Authority: High Court of Karnataka at Bengaluru
Order Date: 17 November 2026
Case Overview
- Petitioners: Vinith Kumar G.K. (age ~29) and Sanjeev A. Kurup (71) with wife Lata Pillai (67), owners of residential properties in Bengaluru.
- Respondents: Chief Commissioner, Greater Bengaluru Authority (GBA); Commissioner, Bengaluru East City Corporation / GBA; Joint Commissioner, Bengaluru East City Corporation / K.R. Pura Zone‑2, GBA; Assistant Executive Engineer, Mahadevapura Sub‑Division, GBA.
- Both petitioners were served Confirmation Orders under Sections 243[3][e] and 244 of the Greater Bengaluru Governance Act, 2024 and filed appeals under Section 250 (Appeal No. 154/2026 and 153/2026 respectively) before the R1 Chief Commissioner, GBA.
- The GBA authorities initiated proceedings under Section 243[3] alleging construction without a sanctioned plan. Petitioners contend they have applied for sanction plans after being entered in revenue Form A.
- Petitioners sought interim relief to restrain any coercive action (demolition/dismantling) pending the appellate decisions. Counsel for petitioners argued that without such stay, demolition would be precipitative.
- Respondents argued that one petitioner (W.P. 35210/2026) had stopped construction for a year, while the other (W.P. 35234/2026) had completed residential accommodation and would not change the nature of construction pending final outcome.
Final Outcome
- The Court ordered that the respondents shall not take any coercive measures to dismantle or demolish the standing structures on the petitioners’ properties during the pendency of the respective appeals.
- The petitioners were directed not to alter the nature of the properties by recommencing construction or any other change until the final appellate orders are pronounced.
- Both writ petitions are disposed of with the above interim relief.
Topics: Property Law, Urban Governance