Authority: Supreme Court of India
Order Date: 31-08-2026
Case Overview
- Parties: Madhya Pradesh Road Development Corporation Ltd (Petitioner) vs. M/s Jabalpur Corridor Pvt Ltd (Respondent).
- Origin: Application filed under Miscellaneous Application No. 2619/2026, IA No. 254860/2026, seeking extension of time to comply with the judgment and order dated 29‑05‑2026 in Civil Appeal No. 10877/2018.
- Counsel: For petitioner – Attorney General R. Venkataramani, Ms. Mrinal Gopal Elker, AOR Mr. Srajan Yadav, Adv. Ms. Silpi S Swain; for respondent – Senior Advocate Vivek Tankha (appearance not given).
- Bench: Hon’ble Mr. Justice Ujjal Bhuyan and Hon’ble Mr. Justice Atul S. Chandurkar.
- Material: The judgment required MPRDC to pay the remaining amount with accrued interest to Jabalpur Corridor Pvt Ltd.
Final Outcome
- The Court allowed the petition, granting a three‑month extension for the payment.
- The Court expressly stated that no further time will be granted beyond the three months.
- The miscellaneous application is disposed of, and any pending applications are also stood disposed.
- The order was digitally signed by IRAMNAZ on 01‑09‑2026 at 17:08:41 IST (signature not verified).
Topics: Court Order, Payment Extension, Infrastructure Contract