Authority: High Court of West Bengal

Order Date: 24 June 2026

Case Overview

  • Petitioner: Mali Agri-Tech Pvt. Ltd.; Respondents: State of West Bengal, Ranaghat Municipality, and others.
  • Issue: Open vat (large uncovered garbage bin) placed in front of petitioner’s premises, obstructing ingress/egress and posing health hazard.
  • Initial order dated 5 May 2026 directed municipality to file a report; municipality failed to appear, leading to fresh notice on 8 June 2026.
  • Municipality eventually appeared, submitted a report dated 5 June 2026 stating the dumping station had been dismantled; photographs showed station removed but garbage and construction debris remained.
  • Court observed discrepancy between report and photographs and directed immediate removal of remaining garbage and materials.

Final Outcome

  • Court ordered respondent No. 4 (Ranaghat Municipality) to remove garbage and demolished construction materials within 24 hours of communication.
  • Respondent No. 4 must file an affidavit with updated photographs before the Registrar General within 7 days.
  • With no further relief, the writ petition stands disposed.

Topics: Court Order, Municipal Sanitation, Property Access