Authority: High Court of Manipur at Imphal

Order Date: 25 September 2026

Case Overview

  • Petitioner: Jadinliu (applicant)
  • Respondents: State of Manipur and six others
  • Main writ petition: WP(C) No. 131 of 2025
  • Application for impleadment: MC(WP(C)) No. 196 of 2026 filed to include M/s Paratech Construction Pvt. Ltd. as respondent No.8
  • Counsel for petitioner: Ms. P. Sandyarani
  • Learned Government Advocate for state respondents: Mr. S. Niranjan
  • The Court examined the necessity of adding Paratech Construction as a party and concluded it was a necessary party.

Final Outcome

  • The Court allowed the impleadment of M/s Paratech Construction Pvt. Ltd., to be listed as respondent No.8 in the main writ petition.
  • The Court directed that notice be issued to the newly impleaded respondent.
  • The petitioner must serve the notice by speed post within one week and file an affidavit proving service.
  • The Registry is to amend the cause title accordingly.
  • The petitioner must file an amended memo of parties within one week.
  • The application MC(WP(C)) No. 196 of 2026 is disposed of.
  • The main matter is listed for hearing on 25 November 2026.

Topics: Impleadment, Writ Petition, Court Order