Authority: High Court of Jammu & Kashmir and Ladakh at Srinagar

Order Date: 20 November 2026

Case Overview

  • Petitioner: M/s Manoj Ji and Company Pvt. Ltd., a private limited construction company, entered into an agreement dated 15 March 2016 with Northern Railway (respondent) for handling, transportation and delivery of goods from Udhampur Railway Station to Srinagar National Rake Point. The contract was operative from 2 November 2015 to 1 November 2018.
  • Petitioner alleges that it successfully performed the contractual obligations but the respondents withheld payment of Rs 64.80 lakh as cartage and transportation charges and retained a security deposit of Rs 34.00 lakh.
  • During the contract period a criminal investigation was launched against the petitioner but was subsequently dropped.
  • On 5 April 2026 the petitioner served a legal notice invoking the arbitration clause and seeking constitution of an arbitral tribunal; the respondents did not accede to the request.
  • The petitioner filed the present petition under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking appointment of an arbitrator.
  • Respondents objected, contending that the petition is barred by limitation and that the claim is untenable, but they did not dispute the existence of the arbitration clause and asked to be allowed to raise all possible pleas before the arbitrator.

Final Outcome

  • The Court allowed the petition and, with the consent of counsel for both parties, appointed Mr. Javed Iqbal Wani, former Judge of the High Court of Jammu & Kashmir and Ladakh, as the sole arbitrator.
  • The arbitrator shall conduct the proceedings in accordance with the provisions of the Arbitration and Conciliation Act and shall make an award within the time prescribed by the Act.
  • The prescribed arbitration fee and incidental expenses shall be shared by the parties.
  • The respondents are at liberty to raise all possible pleas/objections regarding the subject matter before the learned arbitrator.
  • The Registry is directed to send a copy of this order to the learned arbitrator.

Topics: Arbitration, Construction Contract Dispute, Court Order