Case Details

  • Case Name / Type: Special Leave Petition (Civil) Diary No. 6296/2026
  • Parties: Indi Vivekananda (Petitioner) vs. Mantri Developer Pvt. Ltd. (Respondent)
  • Court / Authority: Supreme Court of India
  • Order / Judgment No.: Not specified
  • Date of Order: 15‑05‑2026
  • Period of Dispute / Violation: Not specified

Parties Involved

  • Petitioner: Indi Vivekananda
  • Respondent: Mantri Developer Pvt. Ltd.
  • Counsel for Petitioner: Sr. Adv. K. Parameshwar, Pallav Mongia (AOR), Srinivas V, Kashish Lalwani, Ishita Nayak
  • Counsel for Respondent: Sr. Adv. Shekhar G. Devasa; additional counsel Manish Tiwari, Thashmitha Muthanna, Rakesh Kini, Nishant Anshul, Rishab Kumar T, Shashi Bhushan Nagar (Devasa & Co., AOR)
  • Bench: Hon'ble Mrs. Justice B.V. Nagarathna, Hon'ble Mr. Justice Ujjal Bhuyan

Issues / Allegations / Violations

  • Petition sought condonation of delay in refiling/curing defects (IA No. 143483/2026).
  • Petition also requested permission to file a lengthy list of dates (IA No. 143490/2026).
  • Execution petitions (Nos. 227/2024, 228/2024, 231/2024) were pending before the XVI Additional City Civil and Sessions Judge, Bengaluru, related to the same dispute.

Findings & Observations

  • The Court examined the applications for condonation of delay and permission to file additional dates.
  • No substantive merits of the underlying dispute were adjudicated; the focus was procedural relief.

Penalties / Settlements / Directions

  • Delay in refiling is condoned.
  • Notice to be issued to the respondent, with a return date fixed for 10‑08‑2026.
  • Stay of further proceedings in Execution Petition Nos. 227/2024, 228/2024, and 231/2024 until further orders.

Corrective Actions & Future Obligations

  • Respondent must comply with the notice and appear by the stipulated date.
  • Execution proceedings remain stayed pending any further direction from the Court.

Final Ruling & Enforcement

  • The Supreme Court granted the relief sought by the petitioner: condonation of delay, issuance of notice, and stay of execution petitions.
  • The matter is to remain stayed until the Court issues further orders, and the respondent must respond to the notice by 10‑08‑2026.