Date: 28.07.2026

Other Operational / Legal / Strategic Disclosures

Arbitration Award Update:

  • The Commercial Court in Dehradun, Uttarakhand, has dismissed two petitions filed by the Public Works Department, Government of Uttarakhand.
  • The petitions were filed under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitration award dated 14.12.2024.
  • The arbitration award is in favour of MBL Infrastructure Ltd. and pertains to the project 'Improvement and Strengthening of Roads in the District of Udham Singh Nagar (Package No. C-2)' in Uttarakhand.
  • The total value of the arbitration award, including interest, is ₹82.77 Crores as of 27.07.2026.
  • The award continues to accrue further interest at a rate of 12% per annum until the date of full payment is made to the company.

Compliance

  • This disclosure is made in compliance with Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.