Authority: High Court of Meghalaya at Shillong
Order Date: 18 November 2026
Case Overview
- Applicants: Union of India (represented by Chief Engineer (AF) Shillong Zone, Elephant Falls Camp, P.O. Nonglyer, Shillong – 793009) and Commander Works Engineer, Air Force, Borjhar, Guwahati, Assam – 781124.
- Respondent: M/s. Bhaskar Construction Co., 5/2 N.C. Sen Avenue, Dum Dum, Kolkata – 700080.
- Proforma Respondent: Brig. S.S. Virdhi (Retd.), former Chief Engineer, Jammu & Kashmir Zone, Director of Works Army, Director of Works Navy, Chandigarh – 160011.
- The application was filed under Section 5 of the Limitation Act, 1963 seeking condonation of a 308‑day delay in filing a revision against the order dated 09‑07‑2025 passed in RFA No. 6 (T) 2017 by the Additional Deputy Commission (Judicial), Shillong.
- Counsel for applicants: Dr. N. Mozika, ASGI with Ms. M. Myrchiang, Adv. Counsel for respondent: Ms. P.D.B. Baruah, Sr. Adv. with Ms. D.L. Marshillong, Adv. and Mr. D.M. Rani, Adv.
Final Outcome
- The Court found sufficient cause and condoned the 308‑day delay.
- The Registry was directed to register and diarise the main revision application and schedule an admission hearing.
- The miscellaneous case was allowed and disposed of.
Topics: Limitation Act, Revision Application, Judicial Procedure