Authority: High Court of Jammu & Kashmir and Ladakh, CJ Court
Order Date: 27 November 2026
Case Overview
- Parties: Petitioner – M/s MLAPLNP Associates (Ajay Singh) represented by advocates Anish Chawla & Akarshan Magotra; Respondent – Jammu Power Distribution Corporation Limited represented by Sr. Advocate Monika Kohli and assisting counsel Tabrez Haq.
- Contract Background: Jammu and Kashmir Power Development Department (JKPDD) floated an IFB on 02‑06‑2019 under RAPDRP‑B. MLAPLNP Associates, as the lowest bidder, received a Letter of Intent on 19‑05‑2026 and a contract dated 09‑07‑2020 for ₹41.58 crore, divided into a Supply Contract and a Services/Erection Contract with a 12‑month completion period.
- Project Execution: The contractor missed the original deadline, obtained an extension to 31‑12‑2021, and completed the work. Completion was acknowledged on 01‑08‑2022.
- Dispute Details: The petitioner submitted price‑variation bills for Package 03 amounting to a total of ₹4,41,61,519 (Bill 1 ₹87,23,016; Bill 2 ₹1,03,77,710; Bill 3 ₹2,50,60,793). The respondent did not pay the dues despite the requirement for verification and recommendation by the Project Management Consultant.
- Prior Litigation: The petitioner filed writ petition WP(C) No. 2261/2023, which the Court dismissed as withdrawn, allowing the petitioner to approach arbitration.
- Arbitration Clause: Clause 39 of the contract mandates arbitration by three arbitrators, with provision for a sole arbitrator if one party fails to appoint within 60 days. The petitioner invoked the clause via letters dated 14‑01‑2026 and 14‑02‑2026; the respondent failed to act.
Final Outcome
- The Court allowed the petition under Section 11(6) of the Arbitration and Conciliation Act, 1996.
- Hon’ble Mr. Justice J P Singh (former High Court Judge) is appointed as the sole arbitrator.
- The arbitrator shall conduct the proceedings in accordance with the Act, charge the prescribed fee and incidental expenses to be shared by the parties.
- The respondent is at liberty to raise all objections before the arbitrator.
- The Registry is directed to send a copy of this order to the learned arbitrator.
- The petition is disposed of.
Topics: Arbitration, Power Project Dispute, Court Order