Authority: National Company Law Appellate Tribunal, Principal Bench, New Delhi

Order Date: July 28, 2026

Case Overview

The National Company Law Appellate Tribunal (NCLAT) Principal Bench heard Comp. App. (AT) (Ins) No. 1771 of 2024 along with two Interlocutory Applications (I.A. No. 6459 of 2024 & I.A. No. 4430 of 2025). The appeal was filed by Maharashtra State Electricity Distribution Company Ltd. (MSEDCL) against Edelweiss Asset Reconstruction Company Ltd. The matter was presented before a bench comprising Justice Mohammad Faiz Alam Khan (Member - Judicial) and Mr. Naresh Salecha (Member - Technical).

Final Outcome

The tribunal adjourned the hearing due to lack of time. The appeal has been listed for the next hearing on September 3, 2026. No substantive arguments were heard or decisions made on this date.

Topics: NCLAT Proceeding, Debt Dispute, Adjournment