Court Order Details

The Hon'ble High Court of Judicature at Bombay issued an order dated August 7, 2026, in connected matters relating to Land Acquisition Reference No. 4 of 1999 concerning MTNL's property situated at Pahadi, Goregaon (East), Mumbai.

Key Court Directives

  • The court permitted claimants to withdraw an amount of ₹20,53,94,364 (Twenty Crores Fifty-Three Lakhs Ninety-Four Thousand Three Hundred Sixty-Four Rupees) deposited by MTNL as the acquiring body towards compensation.
  • The court observed that apart from the aforesaid amount, the balance amount towards interest remains payable.
  • The interest amount is required to be paid within three weeks from the date of the order (i.e., by August 28, 2026).

Conditions and Status

All amounts paid and withdrawn shall remain subject to the final outcome of the appeal preferred by MTNL (the acquiring body). The company is taking appropriate steps in the matter and will make further disclosures as required under SEBI (LODR) Regulations, 2015.