Authority: National Company Law Appellate Tribunal, Chennai (Justice N. Seshasayee, Member (Judicial) and Jatindranath Swain, Member (Technical))

Order Date: 25th November 2026

Case Overview

This proceeding concerns an Interlocutory Application (IA No. 1081/2026) filed within a larger Company Appeal (AT) (CH) (Ins) No. 378/2026. The appellant, Madurai Tuticorin Expressways Limited, sought condonation of a delay in preferring its appeal against the respondent, Canara Bank. The application was specifically for condoning a delay of 13 days, though the tribunal's registry reported the actual delay was 14 days. The respondent, Canara Bank, through its counsel, strongly contended that the reason provided in the appellant's affidavit for the delay was not satisfactory.

The tribunal examined the reasons stated in paragraph 2(f) of the appellant's affidavit and found them to be satisfactory. Consequently, the delay was condoned.

Final Outcome

The application (IA No. 1081/2026) was allowed. The 14-day delay in filing the appeal was condoned. The main appeal (Company Appeal (AT) (CH) (Ins) No. 378/2026) is now listed for an admission hearing on 14th December 2026.

Topics: NCLAT, Delay Condonation, Insolvency Appeal