Authority: The National Company Law Appellate Tribunal, Principal Bench, New Delhi
Order Date: 29th June 2026
Case Overview
This Interlocutory Application (No.4160/2026) was filed by Punjab & Sind Bank (Appellant) against Kunal Structure (India) Pvt. Ltd. (Respondent). The application sought an extension of time for curing defects in the filing of a Memorandum of Appeal. The Appellant had initially e-filed the appeal on 20th April 2026. The NCLAT office scrutinized the filing and intimated the defects to the Appellant on 28th April 2026. The Appellant subsequently re-filed the appeal on 3rd June 2026, resulting in a delay of 29 days from the date the defects were communicated.
Final Outcome
After hearing the Appellant's counsel and perusing the application and office report, the Registrar, Raj Kumar, condoned the 29-day delay in re-filing the Memorandum of Appeal. The reasons provided in the application were found to be sufficient. The case has been directed to be listed before the Hon'ble Bench for admission (fresh case). The Interlocutory Application stands disposed of with this order.
This content pertains to a procedural matter and may not be financially relevant.