Authority: The National Company Law Appellate Tribunal (NCLAT) Principal Bench, New Delhi
Order Date: 24th August, 2026
Case Overview
This Interlocutory Application (IA No.5968/2026) was filed by Rayways Infra Projects Pvt. Ltd., acting through its Suspended Director Rajni Gulati, against Superwave Communication and Infrasolution Pvt. Ltd. The application sought an extension of time for curing defects in a memorandum of appeal. The factual background states that the Appellant e-filed the Memo of Appeal on 10th July 2026. The NCLAT office scrutinized the filing and intimated the defects to the Appellant on 24th July 2026. The Appellant subsequently re-filed the appeal on 18th August 2026.
Final Outcome
The Registrar, Raj Kumar, after perusing the averments in the IA and the office report, and considering the reasons mentioned (which were found sufficient), condoned the delay of 18 days in re-filing the Memo of Appeal. The case has been listed before the Hon'ble Bench under the heading 'for admission (fresh case)'. With this order, the interlocutory application stands disposed of.
Topics: NCLAT Procedure, Delay Condonation, Corporate Litigation