Case Details
Case Name: M/s. Apartment Buyers Consumer Association vs. M/s. Dreamz Infra India Limited
Court/Authority: National Company Law Tribunal (NCLT), Bengaluru Bench
Case Number: C.P. (IB) No.113/BB/2022
Interlocutory Applications: I.A. (Plan) 03/2024, 543/2024 in C.P. (IB) No.113/BB/2022
Petition Filed Under: Section 7 of the Insolvency and Bankruptcy Code, 2016
Order Delivered on: 21st May 2026
Coram: Shri Sunil Kumar Aggarwal, Hon'ble Member (Judicial) and Shri Radhakrishna Sreepada, Hon'ble Member (Technical)
Parties Involved
Petitioner: M/s. Apartment Buyers Consumer Association
Respondent (Corporate Debtor): M/s. Dreamz Infra India Limited
Resolution Professional: Mrs. R. Bhuvaneshwari
Counsel for Resolution Professional: Mrs. P. Chithra Nirmala
Counsel for Intervenor in I.A.543/24: Ms. Ragini Bundela
Issues / Allegations / Violations
The matter pertains to the corporate insolvency resolution process of Dreamz Infra India Limited. A specific project, the 'Samhita Project', is under attachment by the Enforcement Directorate (ED). An application from the Resolution Professional for the release of this project is pending consideration before the concerned Special Court that is dealing with the ED matter.
Findings & Observations
The tribunal heard the learned counsel for the parties. After hearing, it passed orders on the two interlocutory applications.
Penalties / Settlements / Directions
- I.A. No.543/2024 was dismissed via a separate order.
- For I.A. (Plan) No.03/2024, the Learned Counsel for the Successful Resolution Applicant (SRA) was directed to file an affidavit stating two things: 1) That they are not acting as an SRA in any other cases, and 2) That they are fully aware of the 'Samhita Project' being attached by the Enforcement Directorate.
- The Learned Counsel for the Resolution Professional was directed to file a brief note regarding the pending application for the release of the project before the Special Court handling the ED matter.
Final Ruling & Enforcement
The case was listed for further orders on 12th June 2026. The proceedings are contingent upon the compliance with the aforementioned directions and the outcome of the application pending before the Special Court concerning the ED attachment.