Case Details

Case Name: M/s.SS Rail Works Pvt. Ltd. vs M/s.VNR Infrastructure Limited (under liquidation)

Court/Authority: National Company Law Tribunal, Hyderabad Bench-II

Case Number: I.A. No.43 of 2022 in C.P.(IB).No.12/10/HDB/2017

Date of Order: 20.05.2026

Period of Dispute: Sub-contract agreement dated 20.02.2015, payments from 2017-2018

Parties Involved

Petitioner/Applicant: M/s.SS Rail Works Pvt. Ltd., represented by its Chief Executive Officer Mr. A. Srinivasulu Reddy

Respondent: M/s.VNR Infrastructure Limited (under liquidation), represented by its Liquidator Mr. T.S.N. Raja

Regulatory Body: North East Frontier Railway Authorities (N.F. Railway)

Tribunal Members: Shri Rajeev Bhardwaj (Member Judicial), Shri Sanjay Puri (Member Technical)

Issues / Allegations / Violations

The Applicant alleged that:

  • They executed subcontract works valued at Rs. 15,36,71,645/- for VNR Infrastructure under a principal contract with N.F. Railway
  • They completed more than 20% of the work and received Rs. 1,21,89,206/- in on-account bills and Rs. 25,91,710/- in PVC bills
  • The Respondent/Liquidator received approximately Rs. 1.45 Crores from NFR Authorities for work executed by Applicant but released only Rs. 1.21 Crores, withholding Rs. 24 lakhs
  • The Liquidator violated Clause 3 of the Sub-Contract Agreement by not releasing payments received from NFR Authorities
  • The Liquidator released payments to other subcontractors (Prakash Enterprises: Rs. 57,78,040; Datta Supply Agency: Rs. 1,60,00,000) without objection but raised issues only with Applicant
  • NFR Authorities were willing to release Rs. 25,91,710/- if final bills and measurements were submitted by Respondent

The Respondent contended:

  • The Sub-Contract Agreement was executed with S&S Enterprises (proprietary concern), not with SS Rail Works Pvt. Ltd.
  • The Applicant had no locus standi to prosecute the claim
  • Bills were not supported by proper Measurement Book extracts or Railway Authority countersignatures
  • Issues existed regarding PVC bills, stock reconciliation, materials, equipment, royalty, termination of contracts, and bank guarantee invocation
  • Connected disputes were pending before NCLAT

Findings & Observations

The Tribunal found:

  • VNR Infrastructure was sold as a going concern for Rs. 12,48,70,000/- through e-auction on 09.03.2020, approved by NCLT on 07.07.2021
  • The sale included project credentials, arbitration receivables and 89 ongoing works in progress
  • The Liquidator was not functus officio and continued to have residual liquidation functions including reconciliation under Section 53 IBC
  • The application sought mandatory directions that would require adjudication of disputed contractual terms (measurements, certification, entitlement, stock reconciliation, royalty, set-off, losses)
  • There was ambiguity regarding assets and contracts transferred under the going concern sale
  • The relief sought went beyond simple liquidation process directions and required substantive contractual adjudication

Penalties / Settlements / Directions

The Tribunal:

  • Dismissed the substantive relief seeking direction to Liquidator to accept measurements, process bills, and release payment
  • Directed the Liquidator to account for this claim while preparing project-wise and litigation-wise status report as per IA No.742 of 2021 directions
  • Directed that if any records relating to Applicant's subcontract works are available with Liquidator, they should be handed over to the present management of VNR Infrastructure
  • Clarified that these directions were for accounting and record transmission purposes only, not admission of claim
  • Left all rights and contentions of parties open

Corrective Actions & Future Obligations

  • Liquidator must include this claim in residual liquidation accounting and reconciliation exercise
  • Liquidator must prepare comprehensive project-wise and litigation-wise status report
  • Liquidator must complete audited/unaudited financial statements, transaction-wise computation of liquidation costs
  • Liquidator must reconcile realizations and distribution, and complete statutory filings

Final Ruling & Enforcement

The application was dismissed with the observation that the Applicant may pursue remedies against:

  • The Corporate Debtor under its present management/successful going-concern purchaser
  • Appropriate contractual, statutory or other competent forum including Railway Authorities
  • The dismissal was without prejudice to the merits of the Applicant's substantive claim