Case Details
Case Name: SREI Equipment Finance Ltd vs. Worlds Window Wardha Infrastructure Pvt. Ltd
Court/Authority: National Company Law Tribunal (NCLT), New Delhi Bench (Court – II)
Case Numbers: IB-222/ND/2024 & IA-2218/ND/2026
Date of Order: May 20, 2026
Matter Under: Section 7 of the Insolvency and Bankruptcy Code (IBC), 2016
Parties Involved
Petitioner/Applicant: SREI Equipment Finance Ltd
Respondent: Worlds Window Wardha Infrastructure Pvt. Ltd
Representative for the Resolution Professional (RP): Advocate Vishawjeet Singh Rathore
Bench: Hon'ble Member (Judicial) Sh. Ashok Kumar Bhardwaj and Hon'ble Member (Technical) Sh. Atul Chaturvedi
Application & Tribunal's Findings
An application (IA-2218/ND/2026) was heard by the tribunal. The learned counsel for the applicant submitted that the Corporate Insolvency Resolution Process (CIRP) is at a culminating stage. It was stated that three proposed resolution applicants have shown interest in submitting a resolution plan, although the plans themselves are yet to be formally received.
Final Ruling & Directions
Based on the submissions and the reasons stated therein, the tribunal allowed the application. The period of the Corporate Insolvency Resolution Process (CIRP) is extended by 90 days beyond its previous deadline of May 16, 2026.