Case Details
- Case Name: C.P. Arora Engineers Contractors Pvt Ltd vs Millennium City Expressways Pvt Ltd
- Court/Authority: National Company Law Tribunal, New Delhi Court-IV
- Case Number: IA/2323/ND/2026 in IB/773/ND/2024
- Date of Order: 25 May 2026
- Legal Provision: Section 9 of the Insolvency & Bankruptcy Code, 2016
Parties Involved
Petitioner/Applicant:
- C.P. Arora Engineers Contractors Pvt Ltd
- Represented by: Adv. Palash S. Singhai, Adv. Harshal Sareen, Adv. Aashima Gautam
Respondent:
- Millennium City Expressways Pvt Ltd (Corporate Debtor)
Tribunal Members:
- Shri Mahendra Khandelwal, Hon'ble Member (Judicial)
- Shri Atul Chaturvedi, Hon'ble Member (Technical)
Issues / Allegations / Violations
The application has been filed by the Interim Resolution Professional (IRP) under Section 19(2) of the Insolvency and Bankruptcy Code, 2016. The specific nature of the directions sought from the tribunal against the respondents is not detailed in this procedural order.
Findings & Observations
This is a procedural order without substantive findings or observations on the merits of the case. The tribunal noted the application and scheduled it for hearing.
Penalties / Settlements / Directions
The tribunal issued the following procedural directions:
- Notice to be issued to the respondents by all means within 03 days
- Respondents are required to file their response and appear before the tribunal
- Proof of service must be filed
Final Ruling & Enforcement
The matter has been listed for the next hearing on 06 July 2026. No final ruling has been delivered in this order, which is purely procedural in nature, scheduling the case for further consideration after receiving the respondent's response.