NCLT directs immediate restoration of electricity supply to Raheja Shilas project, which was disconnected and halting construction.
Interim order requires Resolution Professional to pay outstanding electricity charges and apply for a separate project connection within 15 days.
DHBVN instructed to process the new connection application within one month, with RWA ordered to cooperate in restoration.