Authority: High Court of Himachal Pradesh, Shimla

Order Date: 23 November 2026

Case Overview

  • Petitioner: National Highway Authority of India (NHAI) filed Arbitration Case No. 267 of 2026 seeking extension of time for Arbitration Reference Case No. 560 of 2022, concerning land acquisition in Kangra district for a national highway project under the National Highways Act, 1956.
  • Respondents: Rajnesh and another individual; Respondent No.2 represented by Additional Advocate General Baldev Singh Negi, who waived service of notice.
  • The arbitration was before the Divisional Commissioner‑cum‑Arbitrator, Kangra Division at Dharamshala, appointed under Section 3 of the National Highways Act, 1956.
  • NHAI alleged that the arbitrator failed to pass the award within the statutory period prescribed by the Arbitration and Conciliation Act, 1996, causing undue delay.

Final Outcome

  • The Court held that the arbitrator violated statutory time‑limits and directed the Divisional Commissioner‑cum‑Arbitrator to conclude the arbitral proceedings and pass the award in Arbitration Reference Case No. 560 of 2022 on or before 23 May 2027.
  • The arbitrator is ordered to serve Respondent No.1 through his counsel before proceeding further.
  • The petition is disposed of in these terms.

Topics: Arbitration, Infrastructure