NHPC Ltd has disclosed a significant development in material litigation cases under arbitration, specifically regarding the Parbati-III Hydroelectric (HE) Project (Ref. II).
The disclosure is made in continuation of the company's earlier communication dated August 14, 2023, and in compliance with Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.
Settlement Details
- A settlement agreement has been executed with M/s Patel-L&T Consortium (PLNT)
- The settlement resolves claims related to delay in handing-over of site and adverse geological conditions
- The resolution was achieved through the Conciliation Committee of Independent Experts (CCIE-III)
Financial Terms
- Final settlement amount: ₹42.62 Crore
- Original claim amount by PLNT: ₹256.10 Crore
- Settlement represents an 83.35% reduction from the original claim
- The settlement amount was released by NHPC to PLNT on November 17, 2026
Outcome
Both parties (PLNT and NHPC) have withdrawn their respective claims following the settlement, bringing closure to this arbitration matter.
The disclosure serves as an update on the change in status of material litigation cases and is for information and record purposes.