Authority: Gauhati High Court (High Court of Assam, Nagaland, Mizoram and Arunachal Pradesh)

Order Date: 27 November 2026

Case Overview

  • Case No.: I.A.(Civil)/3478/2026
  • Petitioners: PurNima Barman, Biuti (Beauty) Barman, Dipu Barman – residents of Vill. Sundarbari, Jalukbari, Kamrup (M), Assam.
  • Respondents: Oriental Insurance Co. Ltd and three others; HDFC ERGO General Insurance Co. Ltd (respondent No. 4).
  • Counsel for Petitioners: Mr. A. R. Agarwala and Mr. Aditya Agarwala.
  • Counsel for Respondents: Mr. A. J. Saikia (Standing Counsel for respondent No. 4), Mr. M. Chetia, Mr. A. Das.
  • Presiding Judge: Hon’ble Mr. Justice Parthivjyoti Saikia.
  • Nature of Application: Filed under Section 5 of the Limitation Act, 1963 seeking condonation of a 35‑day delay in preferring the connected appeal.
  • Explanation of Delay: The court examined the petitioner's justification and found it satisfactorily explained.

Final Outcome

  • The court held that issuing a notice to the respondents would be a waste of time.
  • The 35‑day delay was formally condoned.
  • The connected appeal shall be registered and listed for an admission hearing.
  • The standing counsel for HDFC ERGO General Insurance Co. Ltd, Mr. A. J. Saikia, was recorded as representing respondent No. 4.
  • The interim application is disposed of accordingly.

Topics: Limitation Act, Insurance Appeal Procedure, Procedural Order