Authority: High Court of Jammu & Kashmir and Ladakh at Jammu
Order Date: 30 September 2026
Case Overview
- Petition: M/s Pardeep Electricals & Building Private Limited (Petitioner/Appellant), represented by Advocate Arun Dev Singh.
- Respondents: Union of India and others, represented by Advocate Karan Sharma, CGSC and Advocate Vishal Sharma, DSGI.
- Arbitration: Arb P No. 99/2026, Caveat No. 2080/2026.
- The arbitrator had heard the matter, reserved it for a final award, but the award had not been drawn before the arbitral tribunal’s mandate expired on 06.09.2026.
Final Outcome
- The High Court discharged Caveat No. 2080/2026.
- The Court extended the arbitral tribunal’s mandate for an additional two months from 06.09.2026, allowing the arbitrator to conclude the proceedings and issue the final award.
- The matter is disposed of in this manner.
Topics: Arbitration, Court Order