Authority: Supreme Court of India
Order Date: 26-10-2026
Case Overview
- Appellant: Punjab State Power Corporation Limited
- Respondents: Radiance Punjab Renewable Private Limited and others
- Civil Appeal No.: 13092/2026
- Bench: Hon'ble Mr. Justice Aravind Kumar and Hon'ble Mr. Justice Vipul M. Pancholi
- The matter was called for hearing on 26 October 2026; counsel for both sides were listed.
- The petition filed by the appellant was found to have an unverified signature, prompting the Court to intervene procedurally.
Final Outcome
- The Court ordered that a notice be issued to the parties because the signature on the petition was not verified.
- Counter‑affidavit, if any, shall be filed within six weeks of this order.
- Rejoinder affidavit, if any, shall be filed within two weeks after the counter‑affidavit.
- The appeal is to be tagged along with Civil Appeals Nos. 3930/2019 and 6808/2025 for consolidated consideration.
- The order was digitally signed by Rahul Kumar on 27‑10‑2026 at 16:56:18 IST.
Topics: Legal Procedure, Power Sector