Authority: High Court of Uttarakhand at Nainital

Order Date: 18 November 2026

Case Overview

  • Petitioner: Rama Gupta Constructions, a construction firm, filed a writ petition (Misc. Single No. 3310 of 2026) seeking payment of pending dues for the Purkul Village to Bhitarwali‑Kimari Motor Road project.
  • Respondents: State of Uttarakhand, Pradhan Mantri Gram Sadak Yojana, Chief Engineer of Uttarakhand Rural Roads Development Agency, and Executive Engineer.
  • The petitioner claimed entitlement to the amount reflected in the 6th Running/Variation Final Bill, including Rs 1,03,47,321.75 (inclusive of GST), and sought mandamus for payment, item‑wise deduction details, interest at 18% p.a., and costs.
  • The Department indicated willingness to release Rs 50.78 lakh (including GST) while disputing Rs 52.68 lakh, citing a change in road alignment leaving a 675‑metre stretch and directing the petitioner to approach the Dispute Redressal Committee under Clause 24.2 of the contract.

Final Outcome

  • The Court directs the Department to release the admitted amount of Rs 50.78 lakh with GST to the petitioner within four weeks from the order date.
  • The petitioner is permitted to raise a dispute concerning the remaining Rs 52.68 lakh before the Contract’s Dispute Redressal Committee; the Committee must adjudicate the claim within six months of the dispute’s filing.
  • All pending applications, if any, are disposed of.

Topics: Payment Dispute, Infrastructure Contract