Authority: Not specified
Order Date: 17 July 2026
Case Overview
- Parties: Raman Singh (petitioner) vs Himachal Pradesh State Electricity Board Limited (HPSEBL) and others.
- Counsel: Petitioner represented by Advocate A.K. Gupta; respondents represented by Advocates Uday Singh and V.S. Kanwar.
- Proceedings: Hearing held on 17 July 2026 before Judge Ajay Mohan Goel.
- Issues: Application under CMP No. 17000 of 2026 and CMP No. 14214 of 2025 were considered.
Final Outcome
- The court dismissed CMP No. 17000 of 2026, stating the application was not pressed and closed the matter.
- For CMP No. 14214 of 2025, the case was listed for hearing after six weeks with directions that pleadings be completed in the interim.
Topics: Court Proceedings, Power / Utilities