Authority: High Court of Judicature at Bombay, Circuit Bench at Kolhapur
Order Date: October 19, 2026
Case Overview
- Petition: M/s. Rieter India Pvt. Ltd. (Petitioner) vs. The State of Maharashtra, represented by the Industry, Energy and Labour Department, and another respondent (Writ Petition No. 3132 of 2014).
- Interim Application: No. 1886 of 2024 filed by Reiter India Employees Federation, C/o Yogesh Ashok Kamkar, seeking relief in the same matter.
- Judges hearing the matter: Hon’ble Justices Sharmila U. Deshmukh and Abhay J. Mantri.
- Counsel for the State: Mr. Karan S. Thorat, Additional Government Pleader.
- The petition was deemed abandoned due to non‑prosecution; consequently, the interim application could not be entertained.
Final Outcome
- The writ petition is dismissed for non‑prosecution.
- The interim application is disposed of without any further consideration.
- No orders or relief are granted to the petitioners.
Topics: Legal Dismissal, Labor Relations