Authority: Supreme Court Special Lok Adalat

Order Date: 22 August 2026

Case Overview

  • Parties: RKG Industries LLP (petitioner) vs Uttar Pradesh Power Corporation Limited & Others (respondents).
  • Origin: Petition for Special Leave to Appeal (C) Nos. 20360‑20361/2023, arising from impugned final judgment and order dated 30‑09‑2022 in WC No. 23940/2022, and subsequent orders (CMRA No. 129/2023) of the Allahabad High Court.
  • Proceedings: The petitioners sought relief against the respondents; the court examined a settlement deed which was described as defective.
  • Findings: The court recorded that despite the defect, the petitioner had cleared the entire dues owed to the respondent, substantiated by an affidavit filed and admitted into the record.

Final Outcome

  • The Special Leave Petitions were disposed of as infructuous.
  • An award confirming that no dispute remains between the parties was passed.
  • The order effectively closes the litigation, confirming full payment by RKG Industries LLP to Uttar Pradesh Power Corporation Limited.

Topics: Legal Settlement, Power Sector