Authority: Supreme Court of India
Order Date: 25-09-2026
Case Overview
- Petition for Special Leave to Appeal (C) No. 14005/2026 filed by M/S Royal Construction Company Pvt. Ltd (Petitioner) against M/S National Projects Construction Corporation (Respondent).
- The petition challenges the final judgment and order dated 16-02-2026 passed by the High Court of Delhi in EFAOS No. 17/2018.
- Hearing was conducted on 25-09-2026 before a two‑judge bench comprising Hon'ble Mr. Justice Vikram Nath and Hon'ble Mr. Justice Sandeep Mehta.
- Counsel for the petitioner: Mr. Sarvam Ritam Khare, AOR Mr. Kushagra Sharma, Adv. Mr. Saransh Maheshwari. Counsel for the respondent: Mr. Himanshu Sharma‑2801, AOR.
Final Outcome
- The Supreme Court ordered that the petition be not taken up for hearing.
- The matter was listed for further consideration on 09-10-2026.
Topics: Court Proceedings, Construction Dispute