Authority: High Court of Jammu & Kashmir and Ladakh at Jammu
Order Date: 05 August 2026
Case Overview
- Petition filed by M/S Saint Solider Engineer and Contractor Pvt. Ltd. (appellant) represented by Advocate Manik Bhardwaj.
- Respondent: Bhupinder Kumar, Commissioner/Secretary, Public Works Department, and others; no counsel appeared for respondents.
- The petition sought relief in a contempt proceeding (CCP(S) No. 213/2025 in WP(C) No. 2567/2022).
Final Outcome
- The Court observed that a consideration order had already been passed and therefore ordered the contempt proceedings to be closed on 05.08.2026.