Authority: Supreme Court of India

Order Date: 24-09-2026

Case Overview

  • Petitioners: The Haryana Shehri Vikas Pradhikaran & Ors.
  • Respondent: M/s Power Grid Corporation of India Ltd.
  • The Special Leave Petition (Civil) Diary No. 15083/2026 arose from the impugned final judgment and order dated 03‑04‑2025 in CWP No. 27854/2019 passed by the High Court of Punjab & Haryana at Chandigarh.
  • Pending applications before the Court included IA No. 228474/2026 (condonation of delay), IA No. 228476/2026 (condonation of delay in refiling/curing defects), and IA No. 228475/2026 (exemption from filing C/C of the impugned judgment).
  • Counsel for petitioners: Senior Advocate Vikramjit Banerjee and team; counsel for respondent: Additional Solicitor General (not present) and team.

Final Outcome

  • The Court condoned the delay in filing the pending applications.
  • No ground was found to interfere with the High Court’s order dated 03‑04‑2025; consequently, the Special Leave Petition is dismissed.
  • All pending applications, if any, stand disposed of.
  • The order was digitally signed by Sweta Balodi on 24‑09‑2026 at 17:33:12 IST (signature not verified).

Topics: Legal; Power Sector