Authority: Supreme Court of India
Order Date: 25-11-2026
Case Overview
- Appellant: Nehru Place Hotels and Real Estates Private Limited.
- Respondents: Indian Bank (erstwhile Allahabad Bank) and others, including the Committee of Creditors.
- The appeal arises from impugned final judgment and order dated 02‑09‑2026 in CA Nos. 1591/2026, 1592/2026, 1593/2026 passed by the National Company Law Appellate Tribunal.
- The matter was listed before a two‑judge bench of Justice J.B. Pardiwala and Justice K. Vinod Chandran on 25‑Nov‑2026.
- Counsel for the appellant included Senior Advocate Navin Pahwa and a team of advocates; counsel for the respondent included Solicitor General Tushar Mehta and senior counsel Nina R. Nariman.
Observations / Directions
1. Delay in filing is condoned.
2. Dasti service is permitted for service of documents.
3. Notice is issued to the parties, returnable on 15‑Dec‑2026 for filing additional documents, facts, annexures, appeal, and a lengthy list of dates.
4. The Court clarifies that the pendency of the present Special Leave Petition before the Supreme Court shall not impede the proceedings pending before the National Company Law Tribunal (Principal Bench, New Delhi) concerning the change of the Resolution Professional.
5. All other issues raised in the appeal will be considered on the returnable date of 15‑Dec‑2026.
Final Outcome
- The Supreme Court set procedural timelines, allowed Dasti service, and ensured that the NCLT proceedings on the change of Resolution Professional continue unaffected, with further matters to be addressed on 15‑Dec‑2026.
Topics: Insolvency, Banking