Case Overview

  • Petitioner: M/S SGF Infra Pvt. Ltd., represented by authorized signatory Sudesh Kumar Mengi and counsel Mr. Rahul Pant and Mr. Dhruv Pant.
  • Respondents: Jammu Development Authority and its officials – Vice Chairman, Superintending Engineer, Executive Engineer, and Rupesh Kumar, IAS (Vice Chairman), represented by counsel Mr. Atul Verma and Mr. Adarsh Sharma.
  • Petition (WP(C) No. 3024/2026, CM No. 6664/2026) sought quashing of the technical evaluation of bids uploaded on 18 September 2026 at 02:16 PM on the e‑procurement portal (www.jktenders.gov.in) for NIT No. SE/JDA/e‑NIT/2026‑27/07 dated 10 August 2026 (Tender ID 2026‑HAUDD‑320389‑1), and also quashing the opening of financial bids conducted on 18 September 2026 at 02:25 PM.
  • The tender concerned the “Construction of RCC Nallah passing through Phase‑1 Rajinder Nagar, JDA Housing Colony.”
  • Respondents informed the Court that they had withdrawn the NIT, rendering the matters raised in the petition moot.

Final Outcome

  • The Court held that the withdrawal of the NIT by the respondents made the petition infructuous.
  • The petition, together with any connected applications, was disposed of.
  • Any interim directions previously issued were vacated.