Authority: High Court of Uttarakhand at Nainital

Order Date: 23 November 2026

Case Overview

  • Parties: petitioner Shivam Aggarwal vs. Union of India and others, including respondent No.3 – Municipal Development and Development Authority (MDDA), and respondent No.4 – IMA.
  • Nature of Proceeding: Writ Petition (Misc. Single No. 3505 of 2026) challenging the cancellation of a sanction/permission for construction of a commercial building on land owned by the petitioner in Dehradun.
  • Background: The petitioner applied for permission to construct a commercial building on his plot at Mauza Panditwari, Pargana Pachhwadun, Tehsil and District Dehradun. MDDA granted the permission on 15 November 2025, valid for five years, based on the petitioner’s undertaking to obtain all requisite NOCs.
  • Impugned Order: MDDA issued an order on 15 April 2026 cancelling the previously granted permission without issuing a show‑cause notice or providing an opportunity of hearing to the petitioner.
  • Petitioner’s Submissions: The cancellation was unilateral, violated procedural fairness, and the sanction conferred a valuable right that could not be withdrawn without hearing.
  • Respondent No.3 (MDDA) Submissions: Cancellation was due to an objection from respondent No.4 (IMA) for lack of NOC; petitioner had undertaken to submit NOCs before sanction was granted.
  • Respondent Nos.1 & 4 Submissions: Argued that respondent No.4 should also be given a hearing before any decision affecting the petitioner’s application.
  • Court’s Observations: The sanction was not conditional; cancellation without hearing was impermissible and would have civil consequences. The petitioner was not afforded any opportunity of hearing before the impugned order.

Final Outcome

  • The writ petition is allowed.
  • A writ of certiorari is issued quashing the impugned order dated 15 April 2026.
  • The sanction/permission granted on 15 November 2025 is restored.
  • MDDA is granted liberty to pass a fresh order only after providing a hearing to the petitioner and all other stakeholders.
  • Any pending applications, if any, are disposed of accordingly.

Topics: Construction Permission, Administrative Law, Judicial Review