Authority: Supreme Court of India
Order Date: 10-08-2026
Case Overview
- Appellant: Shree Laxmi Steel; Respondent: RCC Infra Ventures Limited.
- The appeal (Civil Appeal No.17402/2026) arises from the impugned final judgment and order dated 05-02-2026 in CAAT(I) No.201/2026 passed by the National Company Law Appellate Tribunal.
- The appellant seeks condonation of delay in refiling and curing defects of IA No.160424/2026.
- Counsel for the appellant included Mr. Garvesh Kabra, Adv. Mr. Amit Singh, AOR Mrs. Pooja Kabra, Adv. Mrs. Nikita Kabra Jaju, Adv. Mrs. Sujata Upadhya, Adv. Mr. Rajasmit Mondal, Adv. Mr. Ankur Agnihotri.
- Counsel for the respondent not listed.
- Bench: Hon’ble Mr. Justice S.V.N. Bhatti and Hon’ble Mr. Justice Manmohan.
Final Outcome
- The Court, at the request of the appellant, directed that the matter be listed for further hearing on 07-09-2026.
- Court Masters assigned: Court Master (SH) – Sneha Das; Court Master (NSH) – Nidhi Mathur.
Topics: Condonation of Delay, Supreme Court Appeal