Authority: High Court of Uttarakhand at Nainital

Order Date: 07 July 2026

Case Overview

  • Petitioner: M/s Shree Mangalam Buildcon (I) Pvt. Ltd.
  • Respondents: Rail Vikas Nigam Limited and another.
  • Petition Number: Writ Petition (M/B) No. 345 of 2025.
  • Counsel for Petitioner: Sri Piyush Garg, learned counsel.
  • Counsel for Respondents: Sri Virendar Kumar Kaparuwan, learned counsel.
  • Bench: Hon'ble Chief Justice Manoj Kumar Gupta and Hon'ble Justice Subhash Upadhyay.
  • The petitioner challenged the Department’s decision to reject its technical bid for a project awarded by Rail Vikas Nigam Limited.
  • The petitioner alleged that the rejection was erroneous and sought relief, including a stay on the award to the successful bidder.

Final Outcome

  • The Court observed that no stay order was in force in favour of the petitioner; consequently, the successful bidder had already completed the contract.
  • In view of the completed contract and the absence of a stay, the writ petition was deemed infructuous and was dismissed.
  • The Court expressly left the question of the petitioner’s ineligibility open for future consideration.
  • Any pending applications, if filed, were also dismissed.

Topics: Court Proceedings, Public Procurement