Authority: High Court of Karnataka at Bengaluru
Order Date: 26 November 2026
Case Overview
- Petitioners: SMR Builders Pvt Ltd (developer) represented by Resident Director & GPA holder Mr. S. Gopal Reddy.
- Respondents: 1) Karnataka Real Estate Regulatory Authority (K-RA) chaired by its Chairperson; 2) Shri Shailesh Kumar, purchaser of Flat No. 412, E2 Block, SMR Vinay Estella, Yelahanka Hobli.
- Background: Agreement of sale dated 10‑05‑2017 required possession within 24 months plus 6‑month grace (by 10‑11‑2019). Project completed on time; other buyers took possession from 11‑09‑2019. Respondent 2 delayed taking possession until 26‑06‑2020, obtained sale deed, and occupied on 21‑03‑2021.
- Complaint: On 21‑03‑2022 Respondent 2 filed a complaint with K-RA seeking compensation for delay and interest. K-RA posted matter for objections on 25‑07‑2023; no hearing occurred; order dated 07‑10‑2023 (CMP/211219/0008736) directed petitioner to pay Rs 15,68,344 as delayed period interest calculated at MCLR 2% from 12‑05‑2019 to 21‑03‑2022, plus interest.
- Petition sought: (i) declaration that undated guidelines (Annexure‑M) on refund with interest and delayed period interest are ultra vires; (ii) quash of order CMP/211219/0008736; (iii) quash of email notice dated 13‑12‑2023 (Annexure‑P); (iv) any other appropriate relief.
- Petitioner argued lack of jurisdiction of K-RA to adjudicate compensation claims under Sections 12, 14, 18, 19 of the RERA Act, which must be decided by a judicial Adjudicating Officer (District Judge). Cited Supreme Court judgments in M/s. New Tech Promoters & Developers Pvt Ltd v. State of Uttar Pradesh and Bombay High Court in Marvel Landmarks Pvt Ltd v. State of Maharashtra.
- Respondent 1 contended it had authority under Section 31(2) of the RERA Act to prescribe complaint procedures and interest rates, and relied on a notification dated 10‑03‑2022 constituting additional benches.
- The Court examined procedural records: notice of proceedings issued 01‑04‑2023, hearing dates 29‑04‑2023 (postponed to 27‑06‑2023), further adjournment to 25‑07‑2023, and order passed after 2½ months without giving Respondent 2 an opportunity to file objections, violating natural justice.
- The Court evaluated the scope of K-RA’s powers versus the Adjudicating Officer’s exclusive jurisdiction for compensation, referencing paragraph 85 of the New Tech judgment, concluding that the relief sought (interest on delayed period) falls within K-RA’s jurisdiction, but the procedural deficiencies render the order invalid.
Final Outcome
1. The writ petition is allowed.
2. The order dated 07‑10‑2023 (CMP/211219/0008736) passed by K-RA is quashed.
3. The matter is remitted to K-RA for fresh consideration in accordance with Section 18 of the RERA Act read with sub‑Rule 2 of Rules 29 of the Karnataka Real Estate (Regulation and Development) Rules 2017.
4. K-RA is directed to issue a suitable corrigendum or amended notification regarding the members delegated to head the various benches whenever there is a change in composition.
5. K-RA is directed to issue necessary guidelines (replacing the undated Annexure‑M) mandating strict adherence to Rules 29 and 30 of the Karnataka Real Estate (Regulation and Development) Rules 2017 while adjudicating complaints.