Authority: National Company Law Appellate Tribunal Principal Bench, New Delhi
Order Date: 25th November, 2026
Case Overview
This interlocutory application (IA No.8400/2026) was filed by Sonajuli Plantations Pvt. Ltd. & Anr. (Appellants) seeking extension of time granted for curing defects in their appeal filing against Ashish Giria, Resolution Professional of Hanuman Tea Company Ltd. (in CIRP). The appellants had e-filed the Memo of Appeal on 29th July 2026. The NCLAT office scrutinized the appeal on 17th August 2026 and intimated defects to the appellants on the same day. The appellants refiled the appeal on 2nd November 2026, citing extensive defects that required complete re-pagination, fresh bookmarking, separation of IAs, replacement of handwritten and vernacular pages with typed English copies, fresh execution of all documents including memo of appeal, vakalatnama, declarations, verifications and affidavits by both appellants, and affixation of requisite court fee and welfare fund stamps. The appellants attributed the 72-day delay to their residence in Kolkata and the time required for re-execution of documents and transmission to counsel.
Final Outcome
The Registrar noted that appellants were required to refile the Memo of Appeal within seven days from the date of defect intimation (17th August 2026), but refiled with a delay of 70 days. The case has been directed to be placed before the Hon'ble Bench under the heading 'for admission with defect (fresh case)' for appropriate orders regarding the condonation of delay application.
Topics: NCLAT Procedure, Appeal Defects, Time Extension