Authority: Supreme Court of India

Order Date: 12-10-2026

Case Overview

  • Appellant: M/S. Sri Bajrang Wind Park Developers; Respondents: M/S. Inox Wind Infrastructure Services Limited & Others.
  • The appeal arises from the impugned final judgment and order dated 02‑03‑2026 in CAAT(I) No. 630/2024 passed by the National Company Law Appellate Tribunal.
  • The appellant filed IA No. 287356/2026 seeking condonation of delay in refiling/curing the defects.
  • Counsel for the appellant: Mr. Aslam Ahmed Jamal (Advocate on Record 3381), Ms. Ankita Sharma (AOR), and senior advocates Mr. Rohit Jain, Mr. Abhishek Dwivedi, Mr. Satyapal Singh, Mr. Mohd Riaz.
  • Counsel for the respondents was not listed in the record.
  • Bench: Hon’ble Mr. Justice S.V.N. Bhatti and Hon’ble Mr. Justice N.V. Anjaria.

Final Outcome

  • The Court, at the request of the appellant, ordered that the matter be listed for further hearing on 26‑11‑2026.

Topics: Court Proceedings, Wind Energy