Authority: Supreme Court of India

Order Date: 16-09-2026

Case Overview

  • Parties: Petitioner – Mintech Global Pvt. Ltd.; Respondent – UltraTech Cement Ltd.
  • Counsel for Petitioner: Mr. Lalit Chauhan, Ms. Laxmi Chauhan, Mr. Manish Yadav, Mr. Anith Johnson, Mr. Rustam Singh Chauhan, Ms. Mrinal Gopal Elker (AOR).
  • Counsel for Respondent: M/S. Khaitan & Co., AOR Mr. Ajay Bhargava, Ms. Vanita Bhargava, Mr. Aseem Chaturvedi, Mr. Shivank Didi.
  • Bench: Hon'ble Mr. Justice Pamidighantam Sri Narasimha and Hon'ble Mr. Justice Alok Aradhe.
  • Nature of Petition: Special Leave Petition (Civil) Diary No. 33175/2026 seeking:
  • IA No. 253199/2026 – Condonation of delay in refiling.
  • IA No. 253194/2026 – Permission to file a lengthy list of dates.
  • Background: The petition arises from an impugned final judgment and order dated 16-03-2026 in AO‑COM No. 6/2025 passed by the High Court at Calcutta.

Final Outcome

  • The Court, after hearing counsel, granted an adjournment on the ground of personal difficulty faced by the petitioner’s counsel.
  • The matter is listed for further hearing on 09-10-2026.

Topics: Legal Proceedings, Cement Industry