Authority: Supreme Court of India

Order Date: 28-10-2026

Case Overview

  • Parties: Swapanesh Sherlekar (Petitioner) vs. M/s Parmesh Constructions & Ors (Respondents).
  • Origin: The Special Leave Petition arises from impugned final judgments and orders dated 14-11-2025 in PILWP No.1884/2024 and PILWP No.2020/2025, and a further order dated 27-04-2026 in CAR No.1/2026, all passed by the High Court of Judicature at Bombay at Goa.
  • Interim Applications (IA): IA No.319322/2026 (condonation of delay), IA No.319323/2026 (exemption from filing copy of the impugned judgment), IA No.319316/2026 (permission to file additional documents/facts/annexures), IA No.319317/2026 (permission to file petition).
  • Hearing: The matter was called for hearing on 28-10-2026 before a bench comprising the Chief Justice, Hon'ble Mr. Justice Joymalya Bagchi, and Hon'ble Mrs. Justice V. Mohana.

Order Details

1. Permission to file the Special Leave Petition is granted.

2. The delay in filing is condoned.

3. Notice is to be issued, returnable on 04.11.2026.

4. Filing of Dasti (additional document) is permitted.

5. The case is to be tagged with C.A. No.2135/2024 for further procedural linkage.

Final Outcome

The Supreme Court has authorized the petitioner to proceed with the Special Leave Petition, waived the procedural delay, mandated a notice to be returned by 4 November 2026, allowed the inclusion of additional documentation (Dasti), and linked the matter with CA No.2135/2024 for subsequent handling.

Topics: Legal Proceedings, Special Leave Petition