Authority: Supreme Court of India
Order Date: 01-07-2026
Case Overview
- Petition: M/s Gridco Limited filed a civil appeal (Diary No. 15312/2026) challenging the final judgment and order dated 16-12-2025 passed by the Appellate Tribunal for Electricity, New Delhi (IA No. 710/2024 and IA No. 980/2025).
- Respondents: Odisha Electricity Regulatory Commission and others.
- The appeal also sought condonation of delay in filing IA No. 161512/2026, condonation of delay in refiling/curing defects IA No. 161510/2026, and ex-parte ad-interim relief IA No. 161508/2026.
- Hearing was held on 01-07-2026 before a partial bench of Hon'ble Mr. Justice Nongmeikapam Kotiswar Singh and Hon'ble Mr. Justice N.V. Anjaria.
Final Outcome
1. The Court condoned the delay in filing the interlocutory applications.
2. The Court directed that a notice be issued to the respondents, which must be returned within four weeks.
Topics: Legal Proceedings, Electricity Regulation