Authority: Supreme Court of India

Order Date: 04-08-2026

Case Overview

  • Petitioner: Bharatiya Kamgar Karmachari Mahasangh
  • Respondent: Emerson Climate Technologies (India) Private Limited
  • Origin: Special Leave Petition (Civil) Diary No. 23351/2026 arising from impugned judgment and order dated 05-05-2025 in WP No. 3761/2025 of the High Court of Bombay.
  • Hearing Date: 03-08-2026.
  • Coram: Hon'ble Chief Justice Joymalya Bagchi, Hon'ble Justice V. Mohana, and Hon'ble Justice (unspecified) (the record lists two Justices).
  • Counsel for Petitioner: M. Y. Deshmukh (Advocate on Record), Ms. Manjeet Kirpal (AOR), Adv. Ms. Sanyukta N. Suryawanshi, Adv. Mr. D. Aswathaman, Adv. Mr. Atharva D. Kale.
  • Counsel for Respondent: Not listed.
  • Applications Filed: IA No. 208366/2026 (condonation of delay in filing), IA No. 208364/2026 (condonation of delay in refiling/curing defects), IA No. 208365/2026 (exemption from filing C/C of the impugned judgment), IA No. 208369/2026 (exemption from filing O.T.), IA No. 208370/2026 (permission to file additional documents/facts/annexures).

Order

1. The Court condoned the delay sought to be condoned in the various interim applications.

2. The Court directed that a notice be issued to the respondent, Emerson Climate Technologies (India) Private Limited, with the notice returnable on 28-09-2026.

Final Outcome

  • The petitioner's delay in filing the Special Leave Petition and related applications was formally condoned by the Supreme Court.
  • A notice has been ordered to be served on the respondent, with a stipulated return date of 28 September 2026, thereby allowing the proceedings to continue.

Topics: Legal Proceedings, Labor Dispute