Authority: Supreme Court of India

Order Date: 13 August 2026

Case Overview

  • Petitioners: RDS Projects Limited & others (collectively "Petitioner(s)")
  • Respondent: Cynosure Electric Company Limited ("Respondent(s)")
  • Petition: Special Leave Petition (C) No. 26591/2026, arising from the impugned final judgment and order dated 07‑07‑2026 in OPC No. 3004/2025 passed by the High Court of Kerala at Ernakulam.
  • Hearing: Petition called for admission on 11‑08‑2026 before a bench of Hon'ble Mr. Justice Aravind Kumar and Hon'ble Mr. Justice Vipul M. Pancholi.
  • Counsel for petitioner sought an enlargement of time to deposit the amount, as the time granted by the lower courts had expired.

Observations & Reasoning

  • The Court found no good ground to entertain the Special Leave Petition.
  • Considering the petitioner's request and the fact that the petitioner had been prosecuting the cause before the Supreme Court, the Court exercised discretion to grant a time extension.
  • The extension period was set at four weeks from the date of the order.
  • Consequently, the Special Leave Petition was dismissed.
  • The Court directed that any pending applications, if any, shall stand disposed of.

Final Outcome

  • The Special Leave Petition (C) No. 26591/2026 is dismissed.
  • Petitioner is granted a four‑week extension, from 13‑08‑2026, to deposit the required amount.
  • All pending applications, if any, are disposed of.

Topics: Legal Dispute, Court Order, Time Extension