Authority: Supreme Court of India

Order Date: 12‑08‑2026

Case Overview

  • Petitioners: Assistant Commissioner ST & Ors.
  • Respondent: M/s. Siemens Gamesa Renewable Power Private Limited.
  • The Special Leave Petitions (Civil) Diary No. 31257/2026 arise from impugned final judgment and order dated 03‑12‑2025 in WP Nos. 4799/2022, 4801/2022, 17132/2024, 17177/2024 passed by the High Court of Andhra Pradesh at Amravati.
  • Applications IA No. 195746/2026 (exemption from filing C/C of the impugned judgment) and IA No. 195747/2026 (condonation of delay in filing IA No. 195746/2026) were listed.
  • The matter was heard on 12‑08‑2026 before a two‑judge bench of Hon’ble Mr. Justice Aravind Kumar and Hon’ble Mr. Justice Vipul M. Pancholi.
  • Counsel for petitioners included Mr. Sahil Bhalaik, AOR Mr. Tushar Giri, and advocates Siddharth Anil Khanna, Ritik Arora, Shivam Mishra, Mihir Joshi.

Final Outcome

  • The Court condoned the delay in filing the application.
  • It found no grounds to interfere with the High Court’s judgments and orders.
  • The Special Leave Petitions were dismissed.
  • Any pending applications, if any, were ordered disposed of.
  • The order was digitally signed by Court Master Neha Gupta on 12‑08‑2026 at 17:12:01 IST (Signature Not Verified).

Topics: Legal Decision, Renewable Energy