Authority: Supreme Court of India
Order Date: 18 November 2026
Case Overview
- Parties: Appellant – M/s Marino Dredgeco Limited (contractor); Respondent – The Board of Trustees of the Port of Kolkata (awarder).
- Two civil appeals filed: Appeal No. 14303 (by the awarder) and Appeal No. 14304 (by the contractor), both arising from a Special Leave Petition.
- Background: Original contract was for dredging the river bed and shores at Sagar Island to create a navigation channel and basin, inaugurated on 17‑04‑2001 by the Port Trust Chairman.
- Additional work: On 19‑07‑2000 the Port Trust issued a letter entrusting extra dredging due to 100% siltation, force‑majeure weather, incorrect soil data, and failure to construct protective walls. The additional work was essentially re‑dredging identical to the original scope.
- Arbitration: An arbitral award quantified the amount payable for the additional work. The Single Judge under Section 34 of the Arbitration and Conciliation Act, 1996 affirmed the award dated 03‑11‑2003.
- High Court Modification (Section 37): The Division Bench of the Calcutta High Court modified the award, reducing the payable amount to 50 % of the arbitrator’s quantification and lowering interest to 6 % from 08‑02‑2002, on the ground that the additional work claim exceeded 70 % of the original contract and that the award “shocked the conscience” of the Court.
- Contentions: Contractor’s counsel (R. Anand Padmanabhan, Amitava Mukherjee) argued that the High Court exceeded its limited powers under Section 37 and that the award was based on adequate evidence (measurements, invoices) and could not be termed perverse or illegal. Port Trust counsel (Siddharth Bhatnagar) sought complete set‑aside of the award, invoking public‑interest considerations.
- Evidence: It was admitted that the original contract value was Rs 2,86,56,200, of which Rs 2,79,32,865 had already been paid. No completion certificate was issued under the General Conditions of Contract (GCC), but the contractor had produced pre‑ and post‑work level measurements supporting the additional work claim.
- Legal Precedents Cited:
- Gayatri Balasamy v. M/s ISG Novasoft Technologies Ltd (2025) – limits on Section 37 interference.
- Batliboi Environmental Engineers Ltd. v. Hindustan Petroleum Corp. Ltd. – quantification must not be whimsical.
- Ssangyong Engineering & Construction Co. Ltd. v. NHAI (2019) – interference only when award conflicts with basic notions of morality or justice, with substantive reason.
- Somdatt Builders–NCC–NEC (JV) v. NHAI (2025) – mere expressions like “shocking the conscience” insufficient for modification.
- Pam Developments Private Ltd. v. State of West Bengal – equality of parties irrespective of government status.
- Gayatri Balasamy – partial set‑aside not feasible when valid and invalid portions are inseparable.
Final Outcome
- The Supreme Court set aside the impugned High Court judgment under Section 37.
- The contractor’s appeal (Civil Appeal No. 14304) is allowed; the arbitral award is restored in full, including the original quantum and interest terms.
- The Port Trust’s appeal (Civil Appeal No. 14303) is disposed of as the order it challenged has been nullified.
- Any pending applications, if any, are ordered disposed.
Topics: Arbitration, Construction Contracts