Authority: Supreme Court of India

Order Date: 03-09-2026

Case Overview

  • Parties: M/S DNC Infrastructure Pvt. Ltd & Anr (Petitioner) vs Union of India & Others (Respondent).
  • Origin: Petition challenges the High Court of Rajasthan judgment dated 29‑04‑2026 in DBCWP No.2744/2026.
  • Relief Sought: Condonation of delay in refiling/curing defects and permission to file additional documents, facts, and annexures.
  • Counsel for Petitioners: Arjun Krishnan (lead counsel), AOR Priyansh Arora, Advocates Mayank Taparia and Purushothaman R.
  • Counsel for Respondents: Mr. V. Chandrashekhar Bharti, who normally appears for the concerned department.
  • Bench: Hon'ble Mr. Justice K.V. Viswanathan and Hon'ble Mr. Justice Arun Palli.

Final Outcome

  • The Court heard the petitioner's counsel.
  • It directed that a copy of the petition be served to Mr. V. Chandrashekhar Bharti, counsel for the department.
  • The matter was listed for further hearing on 09‑Oct‑2026.
  • No substantive decision on the condonation of delay or permission to file additional documents was rendered at this stage.

Topics: Legal Proceedings, Infrastructure