Authority: Supreme Court of India
Order Date: 16-11-2026
Case Overview
- Petitioners: Greater Noida Industrial Development Authority (GIDA) & ANR; Respondents: M/s Tanisha Builder (P) Ltd & others.
- Dispute stems from land allotted in 2003 for an industrial park; Rs 4.96 crore paid. In 2011 a smaller parcel was offered for roughly Rs 3 crore; possession issues with farmer occupants, vacant possession reportedly given in 2018.
- GIDA issued demand notice on 08‑02‑2019, a further notice on 16‑08‑2021 granting one year to complete construction, and an order on 10‑01‑2022 seeking vacant possession; revision petition dismissed on 09‑05‑2023.
- High Court set aside the 2019 demand and the 2022 and 2023 orders on the ground that the notice period had not expired, leading to the present Special Leave Petition.
Final Outcome
- The Supreme Court declines to interfere with the High Court’s setting aside of the orders, stating the decision was based on procedural time‑limit grounds, not merits.
- The Court grants the petitioner liberty to pursue further action in accordance with law, provided it issues a detailed notice specifying monetary heads and affords the respondents a personal hearing before any new order.
- The Special Leave Petition is disposed of; any pending applications are rejected.
Topics: Land Lease Dispute, Court Order