Authority: Supreme Court of India (Civil Appellate Jurisdiction)

Order Date: 18 November 2026

Case Overview

  • Parties: Power Grid Corporation of India Ltd (appellant) vs. Tamil Nadu Generation and Distribution Corporation Ltd (TANGEDCO) and Moxie Power Generation Limited (formerly Coastal Energen Private Ltd) (respondents).
  • Nature of Proceeding: Civil Appeals Nos.14780‑14781 of 2025 challenging the Appellate Tribunal for Electricity (APTEL) order that denied transmission tariff for two Line‑In‑Line‑Out (LILO) assets on the Tuticorin JV‑Madurai 400 kV D/C (Quad) transmission line.
  • Background Facts:
  • Two LILOs (Asset 1 and Asset 2) were commissioned on 04‑01‑2015 and 08‑01‑2015 respectively at the Tuticorin Pooling Station.
  • The generating company (Moxie Power Generation Ltd) built its Dedicated Transmission Line (DTL) to the Tuticorin Pooling Station on 27‑10‑2016.
  • Up‑stream lines from Tuticorin Pooling Station to Salem and Madhugiri Pooling Stations became operational only on 13‑11‑2016 and 01‑12‑2016 respectively.
  • The Central Electricity Regulatory Commission (CERC) approved the Commercial Operation Date (COD) for the LILOs by order dated 29‑07‑2016, based on RLDC trial‑operation certificate and CEA safety certificate.
  • APTEL held the LILOs were not put to beneficial use and imposed a non‑PoC charge of Rs 15,43,26,909 for the period 04‑01‑2015 to 27‑10‑2016.
  • PGCIL contended that the LILOs were permanent infrastructure, approved in the 30th Standing Committee Meeting (05‑05‑2010) and used for evacuating power from the generating stations to TANGEDCO via the Tuticorin Pooling Station.
  • Key Legal Issues:

1. Whether the transmission licensee (PGCIL) is entitled to transmission tariff for the two LILOs spanning ~10 km.

2. Whether APTEL correctly interpreted Regulation 4(3)(ii) of the Tariff Regulations in directing CERC to revisit the COD.

3. Whether the delay in constructing the DTL shifts liability for the period 04‑01‑2015/08‑01‑2015 to 27‑10‑2016 onto the generating company.

  • Observations & Reasoning:
  • The Court examined minutes of the 29th, 30th and 38th Standing Committee meetings, the Bulk Power Transmission Agreements (BPTA), and annexures showing that the LILOs were a permanent part of the transmission plan.
  • RLDC and CEA certificates confirmed that the LILOs were in regular service from the dates stated, satisfying Regulation 3(53) definition of “Regular Service”.
  • Statutory provisions of the Electricity Act (Sections 2, 29(4), 10, 73, 4) and Regulation 4(3)(ii) were interpreted to mean that the COD declared by the transmission licensee is valid when there is no impediment caused by the licensee; the upstream delay does not negate usage.
  • The Court held that the generating company’s DTL delay, not the LILO’s, is the basis for assigning liability, and that the CERC’s allocation of 50 % of the charges to the PoC pool and 50 % to the generating company is appropriate.
  • APTEL’s finding of “no beneficial use” was rejected as factually incorrect; pictorial annexure A‑1 demonstrates electricity flow through the LILOs to the Tuticorin Pooling Station.
  • Precedents cited (Power Grid Corp. v. Madhya Pradesh Power Transmission Co., PTC India Ltd., Energy Watchdog v. CERC) support the Court’s view that CERC’s regulatory orders are binding and that liability can be imposed even absent a Section 178 regulation.

Final Outcome

  • The Supreme Court set aside the impugned APTEL orders in both appeals and restored the CERC order.
  • It affirmed that the two LILOs (Asset 1 and Asset 2) are includable in the transmission tariff from 04‑01‑2015 and 08‑01‑2015 respectively up to the commissioning of the DTL on 27‑10‑2016, on a non‑PoC basis.
  • Liability for the transmission charges is apportioned as per the CERC order: 50 % of the charges are to be borne by the generating company (Moxie Power Generation Ltd) and the remaining 50 % shared under the Point‑of‑Connection (PoC) mechanism.
  • The Court answered the three questions of law: (i) affirmed tariff inclusion (yes), (ii) rejected APTEL’s COD interpretation (no), (iii) confirmed generating‑company liability due to DTL delay (yes).
  • The appeals are allowed; any pending applications stand disposed of.

Topics: Transmission Tariff, Supreme Court Judgment, Electricity Regulation