Authority: Supreme Court of India

Order Date: 20-07-2026

Case Overview

  • Petitioner: Swarn Jyanti Constructions Pvt. Ltd.; Respondent: Nivi Overseas LLP.
  • The petition arose from an impugned final judgment and order dated 14‑May‑2026 passed by the High Court of Delhi in WP(C) No. 4142/2026.
  • Two interlocutory applications were filed: IA No. 199052/2026 seeking condonation of delay in refiling/curing defects, and IA No. 199056/2026 seeking exemption from filing a copy of the impugned judgment.
  • The matter was listed before a two‑judge bench (Justices J.B. Pardiwala and K. Vinod Chandran) on 20‑July‑2026.

Order

1. The Court condoned the delay in filing the petition.

2. After hearing counsel and reviewing the digitally signed record (Harpreet Kaur, 21‑July‑2026 19:24:57 IST), the Court found no sufficient ground to interfere with the High Court’s order dated 14‑May‑2026.

3. Consequently, the Special Leave Petition is dismissed.

4. Any pending applications, if any, are ordered disposed of.

Final Outcome

  • The petition is dismissed; the High Court’s earlier order remains effective; all pending applications are closed.

Topics: Court Decision, Construction Dispute